Cluster wise Achievement Under Rainfed Area Development

Print

Financial Year : 2021-2022, State : HIMACHAL PRADESH, District : SIRMAUR
Cluster(s)Activity(s)PhysicalFinancial (Amount in Rs)
TargetAchievement TargetAchievement TargetAchievement TargetAchievement
UnitUnitUnitCentreStateTotal
Bandli Integrated Farming System
1 Horticulture based farming system Ha 8.00 2,00,000.00 0.00
2 Livestock based farming system
2.1 Dairy based farming system(Cows+Mixed farming+ Fodder,Buffalo+Mixed farming+Fodder Cow/buffalo+dairy) Ha 2.00 80,000.00 0.00
2.2 Small ruminant (Poultry/ duckery+Mixed Farming Poultry/ duckery+Fishery+Mixed/Farming) Ha 3.00 75,000.00 0.00
4 Agro-Forestry/Tree based farming system
4.1 Agro-Foresty based farming system Ha 12.00 1,80,000.00 0.00
4.2 Cropping system with peripheral plantation Ha 180.00 27,00,000.00 0.00
Value Added Resource Conservation System
3 Green house Structure
3.1 Naturally ventilated Tubular Structure Sq.m. 1,219.00 No 390.00 2,38,000.00 0.00
3.4 Plastic Tunnels Sq.m. 75.00 No 105.00 4,000.00 0.00
4 Water Harvesting and Management
4.7 Pipe/pre-cast distribution system Ha 3.00 Running Meter 0.00 30,000.00 0.00
4.8 Water Lifting Devices
4.8.1 Electric No 2.00 30,000.00 0.00
7 Vermi compost Units
7.1 Permanent Structure Cubic Feet 250.00 No 400.00 50,000.00 0.00
7.2 HDPE vermi bed Cubic Feet 16,000.00 No 30.00 2,40,000.00 0.00
11 Capacity building,training & others activities
11.3 Field demonstrations No 7.00 1,00,000.00 0.00
Management Cost
1 Management Cost 30,000.00 0.00
Total of Bandli IFS Area(Ha) 205.00 0.00 39,57,000.00 0.00
Grand Total IFS Area(Ha) 205.00 0.00 39,57,000.00 0.00